Read-only staging package. Nothing here is connected to live email, CRM, calendar, ads, or spend.
L4 · ClickUp breakdown
Project Breakdown
Planning file for the ClickUp board. No ClickUp workspace has been created.
Status snapshot 07-10-2026. The task statuses below are the original plan and are kept as written. Since then: Parts 1–8 are built locally and staged at https://pareto-final-project.pages.dev (22 Link Index URLs tested without login); the CRM and email workflows exist as specifications and a local simulator only (GHL mock, workflows OFF); the Loom (T10.4) is not recorded; no ClickUp board exists. All external systems stay test-only (GoHighLevel test location, mock calendar, workflows OFF).
Timezone for all deadlines: AST (UTC−4).
Deadlines: DATE TO SET until Nazim picks the submission date (Open Question 4). The stated brief deadline was 07-10-2026; working backwards needs a confirmed new date.
Asset IDs (A#) and gap IDs (G#) match Business Map/Asset Register.md and Business Map/Gap Register.md. Dependency IDs (D#) match Dependency Register.md.
Fields
Field
Values
Owner
Nazim, Codex, Claude Code
Status
Not started, In progress, Review, Blocked, Approved
Priority
Critical, High, Medium, Low
Evidence
File path, URL, screenshot, test result, or explicit gap
GATE = a review gate; nothing after it starts until it is Approved. HUMAN CHECK = Nazim approves before any live or public change.
Milestone overview
#
Milestone
Owner
Deadline
Status
Depends on
Evidence
M1
Research and ICP approved
Codex
Done 07-10-2026
Approved
—
Research/ (5 files), Part 1 handoff
M2
Business Map approved
Codex
Done 07-10-2026
Approved
M1
Business Map/
M3
Offer and qualification approved
Nazim
Done 07-10-2026
Approved
M2
Offer/ (Part 4 approval)
M4
Lead magnet content and PDF ready
Claude Code
Done 07-10-2026
Approved
M3
Build/ (app, PDFs, tests, QA report)
M5
Landing page and mini app ready
Claude Code
Done 07-10-2026
Approved
M3, M4, D3, D4
Build/ app and Build/funnel/ QA report
M6
GoHighLevel form, pipeline and workflows ready
Claude Code
DATE TO SET
In progress
M5, D2, D5
Workflow specs or test-location evidence
M7
Mock calendar and booking path ready
Claude Code
DATE TO SET
In progress
M6, D2
Mock booking evidence or test calendar
M8
Five ads and visual system ready
Claude Code
DATE TO SET
Not started
M3, M5, D1
Ad files, brand sheet
M9
Full test run passed
Claude Code
DATE TO SET
Not started
M5–M8
Test report
M10
Loom and final PDF submitted
Nazim
DATE TO SET
Not started
M9
Submission confirmation
Tasks and subtasks
M1 · Research and ICP approved (complete)
ID
Task
Owner
Deadline
Status
Priority
Depends on
Evidence
T1.1
Source index, competitor matrix, ICP, personas, language bank
Claude Code
07-10-2026
Approved
Critical
—
Research/*.md
T1.2
Part 1 recommendation approved
Nazim
07-10-2026
Approved
Critical
T1.1
Research/Part 1 Recommendation.md
T1.3
Run Second Brain retrieval test in a Claude Project
Claude Code
DATE TO SET
Not started
Medium
T1.1
Screenshots of 3 answers vs expected (gap until run)
M2 · Business Map approved (complete)
ID
Task
Owner
Deadline
Status
Priority
Depends on
Evidence
T2.1
Mermaid map, asset register, gap register
Claude Code
07-10-2026
Approved
Critical
M1
Business Map/
T2.2
Map decisions 1–6 settled
Codex
07-10-2026
Approved
High
T2.1
Business Map.md decisions section
T2.3
Fix routing table to match decision 4 ($500K+ = high fit) and A21 tool to match decision 6
Claude Code
DATE TO SET
Not started
Medium
T2.2
Updated Business Map.md, Asset Register.md
T2.4
Publish static map view (SVG/HTML, no login)
Claude Code
DATE TO SET
Not started
High
M5 host (D4)
Public URL, incognito test (A21, G10)
M3 · Offer and qualification approved — GATE
ID
Task
Owner
Deadline
Status
Priority
Depends on
Evidence
T3.1
Final lead-magnet name (MAGIC formula)
Codex
DATE TO SET
Not started
Critical
M2
Part 4 offer file
T3.2
Value Equation write-up (Day 5)
Codex
DATE TO SET
Not started
High
T3.1
Part 4 offer file
T3.3
Final qualification wording and revenue ranges
Codex
DATE TO SET
Not started
Critical
D6
Question list with answer options
T3.4
Next-step offer: why a high-fit founder books the call
Codex
DATE TO SET
Not started
High
T3.1
Copy draft
T3.5
Read-only defect-first review of offer
Codex
DATE TO SET
Not started
High
T3.1–T3.4
Review notes
T3.6
Approve offer
Nazim
DATE TO SET
Not started
Critical
T3.5
Approval note
M4 · Lead magnet content and PDF ready
ID
Task
Owner
Deadline
Status
Priority
Depends on
Evidence
T4.1
Task library: recurring founder tasks with default hours and ease-of-handoff score
Claude Code
DATE TO SET
Not started
Critical
M3
Build/task-library file
T4.1a
— Draft list from Part 1 symptoms and Pareto service scope
Claude Code
DATE TO SET
Not started
High
M3
Draft file
T4.1b
— Label all hour defaults as ASSUMPTION
Claude Code
DATE TO SET
Not started
High
T4.1a
Labels in file
T4.2
Ranking rules (hours × ease) and 3 test profiles with expected output
Claude Code
DATE TO SET
Not started
Critical
T4.1
Test profiles file (A5)
T4.3
Visual system: palette, type, logo use, imagery rules
Claude Code
DATE TO SET
Not started
High
D1
Brand sheet
T4.4
PDF plan template (text selectable, accessible)
Claude Code
DATE TO SET
Not started
Critical
T4.2, T4.3
Template + 3 sample PDFs (A20)
T4.5
Review PDF content and copy
Codex
DATE TO SET
Not started
High
T4.4
Review notes
M5 · Landing page and mini app ready — GATE before publishing
ID
Task
Owner
Deadline
Status
Priority
Depends on
Evidence
T5.1
Choose host for app and pages
Nazim
DATE TO SET
Blocked
Critical
D4
Decision note (G11)
T5.2
Build mini app: task picker, hours, ranked result
Claude Code
DATE TO SET
Not started
Critical
T4.2
Local preview (A4, A7)
T5.2a
— Carry UTMs from URL into app state
Claude Code
DATE TO SET
Not started
High
T5.2
Test with sample UTM URL (A2)
T5.2b
— Pass result and UTMs into GHL form hidden fields or embed
Claude Code
DATE TO SET
Not started
Critical
T5.2, D2
Test submission in test location (G3)
T5.2c
— Fallback: single GHL multi-step form if T5.2b unreliable
Claude Code
DATE TO SET
Not started
Medium
T5.2b
Decision note
T5.3
Build landing page: hero, inside, who it's for, proof, CTA
Test every link in the PDF in incognito; unbuilt = label + dash
Claude Code
DATE TO SET
Not started
Critical
T10.5
Link test log
T10.7
Read-only defect-first review of final PDF
Codex
DATE TO SET
Not started
High
T10.6
Review notes
T10.8
HUMAN CHECK: Nazim submits at bootcamp.paretotalent.com/finalproject
Nazim
DATE TO SET
Not started
Critical
T10.7
Submission confirmation
Emergency four-hour execution schedule
The 23:00 AST deadline is fixed. The four-hour sequence is a target for moving efficiently, not a forced cutoff. Preserve readability and review quality; adjust the estimate after each completed window using actual elapsed time. This schedule assumes sandbox/test-only execution and labels every unbuilt external asset honestly.
Window
Focus
Required evidence
0:00–0:45
Part 4 offer approval: title, promise, Value Equation, qualifiers, routes, CTA
Approved offer files
0:45–1:45
Part 5 lead magnet: working mini-app or local demo plus accessible PDF template and sample output
App preview, PDF, test profiles
1:45–2:30
Parts 6–7 funnel and CRM: landing-page copy, form fields, workflow specs, mock calendar definition
Local preview/spec files, no live activation
2:30–3:15
Part 8 ad copy and visual direction: five distinct Facebook angles with UTMs
Ad copy and visual-system file
3:15–4:00
Part 9 assembly: link index, walkthrough, Loom script, final PDF draft
Final PDF draft and link test log
Final phase
Full read-only review, repair pass, link check, PDF export, and manual submission
Review notes, corrected files, and submission confirmation
Scope rule for the deadline
Prioritize a coherent, reviewable system and the final PDF. Keep GoHighLevel, calendar, email, hosting, ads, and ClickUp in test-only or documented-mock status unless an already available test surface can be completed without risking the deadline. Every unavailable URL must use the exact required label followed by a dash.
Working backwards (standard schedule, if the deadline moves)
Order and relative spacing to use when DATE TO SET is replaced, counting back from submission day (S):
Milestone
Target
M10 submitted
S
M9 test passed
S − 1 day
M8 ads ready
S − 2 days
M6, M7 GHL ready
S − 3 days
M5 page and app published
S − 4 days
M4 PDF ready
S − 5 days
M3 offer approved
S − 6 days
These spacings are an ASSUMPTION based on the execution plan's ~65 hours; adjust to real availability.