L4 · ClickUp breakdown

Project Breakdown

Planning file for the ClickUp board. No ClickUp workspace has been created.

Status snapshot 07-10-2026. The task statuses below are the original plan and are kept as written. Since then: Parts 1–8 are built locally and staged at https://pareto-final-project.pages.dev (22 Link Index URLs tested without login); the CRM and email workflows exist as specifications and a local simulator only (GHL mock, workflows OFF); the Loom (T10.4) is not recorded; no ClickUp board exists. All external systems stay test-only (GoHighLevel test location, mock calendar, workflows OFF).

Fields

Field Values
Owner Nazim, Codex, Claude Code
Status Not started, In progress, Review, Blocked, Approved
Priority Critical, High, Medium, Low
Evidence File path, URL, screenshot, test result, or explicit gap

GATE = a review gate; nothing after it starts until it is Approved. HUMAN CHECK = Nazim approves before any live or public change.

Milestone overview

# Milestone Owner Deadline Status Depends on Evidence
M1 Research and ICP approved Codex Done 07-10-2026 Approved — Research/ (5 files), Part 1 handoff
M2 Business Map approved Codex Done 07-10-2026 Approved M1 Business Map/
M3 Offer and qualification approved Nazim Done 07-10-2026 Approved M2 Offer/ (Part 4 approval)
M4 Lead magnet content and PDF ready Claude Code Done 07-10-2026 Approved M3 Build/ (app, PDFs, tests, QA report)
M5 Landing page and mini app ready Claude Code Done 07-10-2026 Approved M3, M4, D3, D4 Build/ app and Build/funnel/ QA report
M6 GoHighLevel form, pipeline and workflows ready Claude Code DATE TO SET In progress M5, D2, D5 Workflow specs or test-location evidence
M7 Mock calendar and booking path ready Claude Code DATE TO SET In progress M6, D2 Mock booking evidence or test calendar
M8 Five ads and visual system ready Claude Code DATE TO SET Not started M3, M5, D1 Ad files, brand sheet
M9 Full test run passed Claude Code DATE TO SET Not started M5–M8 Test report
M10 Loom and final PDF submitted Nazim DATE TO SET Not started M9 Submission confirmation

Tasks and subtasks

M1 · Research and ICP approved (complete)

ID Task Owner Deadline Status Priority Depends on Evidence
T1.1 Source index, competitor matrix, ICP, personas, language bank Claude Code 07-10-2026 Approved Critical — Research/*.md
T1.2 Part 1 recommendation approved Nazim 07-10-2026 Approved Critical T1.1 Research/Part 1 Recommendation.md
T1.3 Run Second Brain retrieval test in a Claude Project Claude Code DATE TO SET Not started Medium T1.1 Screenshots of 3 answers vs expected (gap until run)

M2 · Business Map approved (complete)

ID Task Owner Deadline Status Priority Depends on Evidence
T2.1 Mermaid map, asset register, gap register Claude Code 07-10-2026 Approved Critical M1 Business Map/
T2.2 Map decisions 1–6 settled Codex 07-10-2026 Approved High T2.1 Business Map.md decisions section
T2.3 Fix routing table to match decision 4 ($500K+ = high fit) and A21 tool to match decision 6 Claude Code DATE TO SET Not started Medium T2.2 Updated Business Map.md, Asset Register.md
T2.4 Publish static map view (SVG/HTML, no login) Claude Code DATE TO SET Not started High M5 host (D4) Public URL, incognito test (A21, G10)

M3 · Offer and qualification approved — GATE

ID Task Owner Deadline Status Priority Depends on Evidence
T3.1 Final lead-magnet name (MAGIC formula) Codex DATE TO SET Not started Critical M2 Part 4 offer file
T3.2 Value Equation write-up (Day 5) Codex DATE TO SET Not started High T3.1 Part 4 offer file
T3.3 Final qualification wording and revenue ranges Codex DATE TO SET Not started Critical D6 Question list with answer options
T3.4 Next-step offer: why a high-fit founder books the call Codex DATE TO SET Not started High T3.1 Copy draft
T3.5 Read-only defect-first review of offer Codex DATE TO SET Not started High T3.1–T3.4 Review notes
T3.6 Approve offer Nazim DATE TO SET Not started Critical T3.5 Approval note

M4 · Lead magnet content and PDF ready

ID Task Owner Deadline Status Priority Depends on Evidence
T4.1 Task library: recurring founder tasks with default hours and ease-of-handoff score Claude Code DATE TO SET Not started Critical M3 Build/task-library file
T4.1a — Draft list from Part 1 symptoms and Pareto service scope Claude Code DATE TO SET Not started High M3 Draft file
T4.1b — Label all hour defaults as ASSUMPTION Claude Code DATE TO SET Not started High T4.1a Labels in file
T4.2 Ranking rules (hours × ease) and 3 test profiles with expected output Claude Code DATE TO SET Not started Critical T4.1 Test profiles file (A5)
T4.3 Visual system: palette, type, logo use, imagery rules Claude Code DATE TO SET Not started High D1 Brand sheet
T4.4 PDF plan template (text selectable, accessible) Claude Code DATE TO SET Not started Critical T4.2, T4.3 Template + 3 sample PDFs (A20)
T4.5 Review PDF content and copy Codex DATE TO SET Not started High T4.4 Review notes

M5 · Landing page and mini app ready — GATE before publishing

ID Task Owner Deadline Status Priority Depends on Evidence
T5.1 Choose host for app and pages Nazim DATE TO SET Blocked Critical D4 Decision note (G11)
T5.2 Build mini app: task picker, hours, ranked result Claude Code DATE TO SET Not started Critical T4.2 Local preview (A4, A7)
T5.2a — Carry UTMs from URL into app state Claude Code DATE TO SET Not started High T5.2 Test with sample UTM URL (A2)
T5.2b — Pass result and UTMs into GHL form hidden fields or embed Claude Code DATE TO SET Not started Critical T5.2, D2 Test submission in test location (G3)
T5.2c — Fallback: single GHL multi-step form if T5.2b unreliable Claude Code DATE TO SET Not started Medium T5.2b Decision note
T5.3 Build landing page: hero, inside, who it's for, proof, CTA Claude Code DATE TO SET Not started Critical M3, T4.3, D1 Local preview (A3)
T5.4 Build thank-you page with resource link Claude Code DATE TO SET Not started High T4.4 Local preview (A15)
T5.5 Mobile, desktop and accessibility check Claude Code DATE TO SET Not started High T5.2–T5.4 QA report
T5.6 Read-only defect-first review before publishing Codex DATE TO SET Not started High T5.5 Review notes
T5.7 HUMAN CHECK: approve publishing pages and app Nazim DATE TO SET Not started Critical T5.6 Approval note
T5.8 Publish and test every URL in incognito Claude Code DATE TO SET Not started Critical T5.7 URLs + screenshots

M6 · GoHighLevel form, pipeline and workflows ready (test location only)

ID Task Owner Deadline Status Priority Depends on Evidence
T6.1 Confirm GHL test location and access Nazim DATE TO SET Blocked Critical D2 Location name (no secrets) (G7)
T6.2 Custom fields for all qualifiers + UTMs Claude Code DATE TO SET Not started Critical T6.1 Screenshot
T6.3 Form with contact + 5 qualifiers + email consent Claude Code DATE TO SET Not started Critical T6.2, T3.3 Form URL (A6)
T6.4 Pipeline stages and tags Claude Code DATE TO SET Not started High T6.1 Screenshot (A19)
T6.5 Opt-in workflow: create opportunity, tag tier, PDF email, notify (OFF) Claude Code DATE TO SET Not started Critical T6.3, T6.4, T4.4, D5 Workflow screenshot (A9–A11)
T6.6 Routing: high → booking page; potential/low → thank-you Claude Code DATE TO SET Not started Critical T6.5, M7 3 test contacts (A8)
T6.7 High-fit follow-up: 2 emails + booking nudge, stops on booking (OFF) Claude Code DATE TO SET Not started High T6.5 Workflow screenshot (A16)
T6.8 Unqualified: 3 educational nurture emails after delivery (OFF) Claude Code DATE TO SET Not started Medium T6.5 Workflow screenshot (A17)
T6.9 Low-fit: same educational nurture, no booking CTA Claude Code DATE TO SET Not started Medium T6.5 Test log (A18)
T6.10 HUMAN CHECK: Nazim reviews every email's exact text Nazim DATE TO SET Not started Critical T6.5–T6.9 Approval note

M7 · Mock calendar and booking path ready (test location only)

ID Task Owner Deadline Status Priority Depends on Evidence
T7.1 Build "Pareto Talent Right Hand Discovery Call" calendar: 30 min, mock availability Claude Code DATE TO SET Not started Critical T6.1 Booking URL (A12)
T7.2 Booking workflow: Call Booked stage, confirmation, reminder (OFF) Claude Code DATE TO SET Not started High T7.1, T6.4 Workflow screenshot (A13)
T7.3 Confirm live Pareto calendar untouched Claude Code DATE TO SET Not started High T7.1 Note

M8 · Five ads and visual system ready (not activated, no spend)

ID Task Owner Deadline Status Priority Depends on Evidence
T8.1 Define ad angles 4 and 5 Codex DATE TO SET Not started High M3 Angle list (G9)
T8.2 Write 5 ads: hook, offer, qualifier, proof, mechanism, CTA Claude Code DATE TO SET Not started Critical T8.1, D1 Ad copy file (A1)
T8.3 Generate on-brand images (check credit balance first) Claude Code DATE TO SET Not started High T4.3, T8.2 Image files
T8.4 Tracking URLs with UTMs per ad Claude Code DATE TO SET Not started Medium T5.8 URL list (A2)
T8.5 Consistency check: ads vs page vs PDF vs emails Codex DATE TO SET Not started Medium T8.3 Review notes

M9 · Full test run passed — GATE before submission

ID Task Owner Deadline Status Priority Depends on Evidence
T9.1 HUMAN CHECK: approve turning workflows on for test contacts only Nazim DATE TO SET Not started Critical M6, M7 Approval note
T9.2 Run 3 test contacts (high, potential, low) end to end Claude Code DATE TO SET Not started Critical T9.1 Test report (stage, tags, emails, redirects)
T9.3 Check no duplicate or looping emails Claude Code DATE TO SET Not started Critical T9.2 Email log
T9.4 Test every URL in incognito, mobile and desktop Claude Code DATE TO SET Not started Critical T9.2 Screenshots
T9.5 Turn workflows back OFF after test unless Nazim approves otherwise Claude Code DATE TO SET Not started High T9.2 Screenshot
T9.6 Read-only defect-first review of whole system Codex DATE TO SET Not started High T9.2–T9.4 Review notes

M10 · Loom and final PDF submitted

ID Task Owner Deadline Status Priority Depends on Evidence
T10.1 Write full SOP from SOP Outline.md Claude Code DATE TO SET Not started High M9 SOP file + public link
T10.2 Build ClickUp board from this file (after approval) Claude Code DATE TO SET Not started High D7 Public ClickUp link
T10.3 Loom script (2 min) Codex DATE TO SET Not started High M9 Script file
T10.4 Record Loom Nazim DATE TO SET Not started Critical T10.3 Public Loom URL (A22)
T10.5 Final PDF: cover, link index with exact labels, walkthrough Claude Code DATE TO SET Not started Critical T10.1–T10.4 FP_NazimSmith_ParetoBootcamp.pdf (text selectable)
T10.6 Test every link in the PDF in incognito; unbuilt = label + dash Claude Code DATE TO SET Not started Critical T10.5 Link test log
T10.7 Read-only defect-first review of final PDF Codex DATE TO SET Not started High T10.6 Review notes
T10.8 HUMAN CHECK: Nazim submits at bootcamp.paretotalent.com/finalproject Nazim DATE TO SET Not started Critical T10.7 Submission confirmation

Emergency four-hour execution schedule

The 23:00 AST deadline is fixed. The four-hour sequence is a target for moving efficiently, not a forced cutoff. Preserve readability and review quality; adjust the estimate after each completed window using actual elapsed time. This schedule assumes sandbox/test-only execution and labels every unbuilt external asset honestly.

Window Focus Required evidence
0:00–0:45 Part 4 offer approval: title, promise, Value Equation, qualifiers, routes, CTA Approved offer files
0:45–1:45 Part 5 lead magnet: working mini-app or local demo plus accessible PDF template and sample output App preview, PDF, test profiles
1:45–2:30 Parts 6–7 funnel and CRM: landing-page copy, form fields, workflow specs, mock calendar definition Local preview/spec files, no live activation
2:30–3:15 Part 8 ad copy and visual direction: five distinct Facebook angles with UTMs Ad copy and visual-system file
3:15–4:00 Part 9 assembly: link index, walkthrough, Loom script, final PDF draft Final PDF draft and link test log
Final phase Full read-only review, repair pass, link check, PDF export, and manual submission Review notes, corrected files, and submission confirmation

Scope rule for the deadline

Prioritize a coherent, reviewable system and the final PDF. Keep GoHighLevel, calendar, email, hosting, ads, and ClickUp in test-only or documented-mock status unless an already available test surface can be completed without risking the deadline. Every unavailable URL must use the exact required label followed by a dash.

Working backwards (standard schedule, if the deadline moves)

Order and relative spacing to use when DATE TO SET is replaced, counting back from submission day (S):

Milestone Target
M10 submitted S
M9 test passed S − 1 day
M8 ads ready S − 2 days
M6, M7 GHL ready S − 3 days
M5 page and app published S − 4 days
M4 PDF ready S − 5 days
M3 offer approved S − 6 days

These spacings are an ASSUMPTION based on the execution plan's ~65 hours; adjust to real availability.